Hi there,
I have to draw fixtures manually from a vectorworks plan inside augmented, because it is 20 years old and fixtures where still made of lines and squares grouped together.
Anyway, it is a lot. So, I used the positions from the vectorworks plan and put it all in the augmented. But when I am draging my fixtures in the hieracy window on the right side into a truss, the position data changes to world data.
For example the fixture data is:
Position X: 13 Y: -1 Z:0
World: XYZ same
when I drag it onto the pipe it becomes:
Potition: X:20 Y:-6 Z:-28
World: X:13 Y:-1 Z:0
I understand that this could be helpful because the origin changed to the pipe but in my case it is a bit annoying. Because all measurements in the Vectorworks Plan is from the origin 0-0.
Is it possible to deactivate this?
Thanks in advance.